India Project

Phase 6: Walls, Floor & Roof Tiles Estimate - $10,600 USD Dispursed funds to date - $3,690.59 USD $500 - $1000 - $3000 - $5000 - $8000 - $10,600
Project Re-Evaluation : All phases are under consistent evaluation due to high inflation and changing supply costs, property delays and staff restructuring. Please continue to pray for the Indian people that will be helped through this project.
DONATE to PHASE 6 DONATE to PHASE 6

Social Media Support

Sharing the Good News of Jesus in Villages
Reaching those in need with hope and care
Project Details : Faith Builders Fellowship is building a church / ministry center to serve the poor people of India and share the power of Jesus’ love and redemption. We are raising funds to complete the project construction to begin use of the facility. Phase Six Details : Interior & Exterior portions of the building is being constructed in this phase. Materials & Labor include: 1. Bricks for Compound Walls - $ 1,700 2. Cement - $ 1,600 3. Sand - $ 1,500 4. Compound Floor - $ 1,450 5. Compound Iron Door - $ 800
Phase 1 Photos & Details Phase 1 Photos & Details Phase 2 Photos & Details Phase 2 Photos & Details
Here comes the tiles!
Here comes the sand!
Here comes the concrete and workers!
Missions team working between projects
Phase 4 Photos & Details Phase 4 Photos & Details Phase 5 Photos & Details Phase 5 Photos & Details Phase 3 Photos & Details Phase 3 Photos & Details
Latest photos are at the bottom of the page.
6. Roof Cool Tiles - $ 750 7. Staircase - $ 850 8. Truck Delivery Charge - $ 250 9. Labor - $ 1,700 Total $ 10,600
$3,690.59 as of April 14, 2026
Tiles will be used throughout the facility
Mixing the concrete and sand
The tile setting begins
This area is looking like a bath area
It takes a lot of materials and labor
Working together to get it all done
Our wonderful ladies who work very hard
Mix, mix, mix the concrete
Soon the floors downstairs will be complete
One tile at a time
One more room completed
The floors are coming together
EK Regi checking out the completed work
More tiles to be installed on the second floor
This is restroom number one
This is restroom number two
Moving to finish the steps is upcoming
Workers are currently setting more tiles
Lots of mixing in each room
Cement on the bottom floor is ready
The floors are looking good
Messy work with beautiful results
One tile at a time
Doors are now being installed
Installation is a messy job, but clean feet
These doors are custom fit for each room
Sanded and stained by our skilled workers
Amazing work throughout the project
Wow! Busy making sparks!
Another door completed
Cooking gas shortage due to the war
Despite the war the work continues
Electrical install ouside and inside
Our electrician installing the conduit
Electrical panel setup
More indoor installation for electric
Back to the tiles! Non stop tile work
Tile work being completed on all floors
Messy work, and this time muddy feet!
When the tiles are in and dried all is good
Completed stairs! Very nice work
More photos coming soon

India Project

Phase 6: Walls, Floor & Roof Tiles Estimate - $10,600 USD Dispursed funds - $3,690.59 USD
Project Details : Faith Builders Fellowship is building a church / ministry center to serve the poor people of India and share the power of Jesus’ love and redemption. We are raising funds to complete the project and begin using the facility. Re-Evaluation : All phases are under consistent evaluation due to high inflation and changing supply costs, property delays and staff restructuring. Please continue to pray for the Indian people that will be helped through this project. Phase Six Details : Interior & Exterior portions of the building is being constructed in this phase. Materials & Labor include: 1. Bricks for Compound Walls - $ 1,700 2. Cement - $ 1,600 3. Sand - $ 1,500 4. Compound Floor - $ 1,450 5. Compound Iron Door - $ 800 6. Roof Cool Tiles - $ 750 7. Staircase - $ 850 8. Truck Delivery Charge - $ 250 9. Labor - $ 1,700 Total $ 10,600
500 - 1000 - 3000 - 5000 - 8000 - 10660
$3,690.59 as of April 14, 2026
Here comes the sand
Sharing the Good News of Jesus in Villages
Here comes the tiles
Missions team working between projects
Reaching those in need with hope and care
Here comes the concrete and workers
Working together to get it done
Mixing the concrete and sand
Tiles will be installed throughout the facility
Tile setting begins
This area looks like a kitchen area
This area looks like a bath area
The floors are coming together
Our wonderful ladies who work very hard
Mix, mix, mix the concrete
Soon the floors downstairs will be complete
Latest photos are at the bottom of the page.
Previous phase photos can be viewed here.
One tile at a time
Tile work throughout the night
One more room completed
EK Regi checks out the work being completed
More tiles to be installed on the second floor
More mixing for the floor tiles
Dedicated workers continue each day
This is restroom number one
This is restroom number two
Each room has a different design
Messy work with beautiful results
One tile at a time
Cement needs to be carried to the upper rooms
The steps will be worked on soon
More photos coming soon
Thank you for considering a donation!
Here comes the doors!
Wow! This work creates sparks!
Each door has to be custom fitted
Each door is sanded and stained
Messy work with beautiful results
Another door completed. Thank God!
Outdoor electric being installed
Our electrician is adding the exterior conduit
… and the inside holes for electricity
More exterior conduit on the second floor
Electrical board being setup. How do we do this?
Back to the tile work - lots of it!
Messy work with beautiful results
Another load of sand for the tile work
It’s all coming together one tile at a time
Second floor tiles being installed
Hurray - The staircase to the second floor is finished
Pray for India - Cooking gas shortage due to war